AI stock research- power/data centers. Electrician/EPC contractor for renewables. Covering IREN, BC Sites-Mackenzie, Prince George, Canal Flats. MORE to come.

$IREN Prince George UPDATE: Thermal imaging shows all 4 data halls and the two substation transformers are humming and drawing significant power. Its raining so some of the heat signature is distorted. More Prince George site specific updates to come. Lots going on there!
48
59
767
110,924
$IREN Mackenzie UPDATE: Thermal imaging from 10/24 shows significant heat coming from data halls 4 and 2. All 8 segments of data hall 4 are showing enough heat to suggest commissioning. With fiber optics still being tied in, however, they are most likely not billing yet. As for hall 2, 6 of 8 segments are showing heat signatures and are most likely being commissioned, yet not billing since fiber optics has not been tied in. Lots of work has been done since 9/23 footage was taken. I believe 3-4 halls could be online and billing before year-end.
18
24
290
15,745
$IREN Mackenzie UPDATE/CORRECTION: Based on new footage of Mackenzie, I am changing my opinion of what the trench and pipes are running along the rear of the data hall. The trench itself is a concrete cable trough for the fiber-optics network. The orange temp buildings you see circled in the new photo are where the workers are building ladder trays for the fiber to enter the building. The pipes that are spaced out equally every 5ft or so are most likely drainage pipes.
Mackenzie UPDATE: $IREN looks to be laying the groundwork for liquid cooling at Mackenzie while the air-cooled retrofit is still underway. Drone footage from 9/23 shows black 2" to 3" rigid pipe entering the data hall wall at regular intervals along an open trench that runs the length of the building. It looks like supply and return branch lines for a liquid cooling system. If you look closely, they go from the wall into buried trunk lines running parallel to the data hall for a future liquid-cooling loop, going in at the same time as the air-cooled GPU fit-out. Why this is smart sequencing:
4
9
141
7,316
🚨BREAKING NEWS🚨 10/24 footage confirms massive expansion is underway at $IREN's Mackenzie site in BC. Will @danroberts0101 discuss this on the 11/5 earnings call? More details to come!
40
67
603
114,398
IREN is partnering with NVIDIA to launch Minerva, NVIDIA’s new AIOps platform, on IREN AI Cloud. Our VP of AI Cloud, Jason Forrester, joins NVIDIA’s Gilad Shainer and 650 Group’s Alan Weckel to explore how IREN’s approach to AIOps enhances visibility, strengthens operations and keeps compute productive. Watch the conversation: youtu.be/MWVjiWYs1sw
1
1
69
2,765
$IREN The way he answered the question about GPU rental prices going up tells me IREN is giving customers better deals based on how much GPU pre-payment they agree to.
IREN’s @danroberts0101 speaks to @ArjunKharpal about AI financing and demand on CNBC. Watch the full interview.
12
2
159
10,247
$IREN Canal Flats UPDATE: Thermal imaging from 10/21 More details to come!
1
8
227
8,246
$IREN Canal Flats UPDATE: Drone footage being taken today, site updates to come, but I am not expecting much change from this site at this time. Picture below is an old google image.
3
2
90
4,018
$IREN The thesis continues its validation process everyday.
A lot of questions this week on funding, so here's how a GPU typically gets funded at $IREN. First, the customer signs a multi-year take-or-pay contract and agrees to a prepayment. On our recent 3-year contracts, prepayments have been 45% to 55% of the associated GPU capex. Second, financing is committed, secured by the contracted GPUs. On the Microsoft contract we secured an A-rated facility at around 6%, which together with prepayments covers 96% of GPU capex. More recently, for a non-investment grade counterparty at Mackenzie, we secured financing at 9% fixed, which together with prepayments covers more than the full cost of the GPUs. That's the GPU side. The data centers are a separate, long-term asset base, and we own the ones our GPUs run in. Construction has been funded from cash to date, with no debt against these multi-billion dollar assets. As they come online with contracted customers, they can support financing in their own right. The processes behind the next facilities are continuing, and new paper will cost what the market charges. With GPU paybacks of around two years on our recent 3-year contracts, a wider spread barely moves the economics. There's more customer demand than we can build for. As we noted at our recent earnings, 2026 is largely sold out, recent 3-year contracts are at more than double the prior year's pricing, and demand for anything we can bring online in 2027 covers it several times over, with prepayments a focus in every negotiation. Conversations on 2028 capacity are already underway. Meanwhile announced capacity keeps slipping across the industry, which is the point: signing deals isn't the bottleneck in this market, bringing GPUs online is, and that's our focus.
2
2
113
5,872
$IREN Read this before jumping to conclusions on the rumors. Thanks @jiahanjimliu
$IREN Status of H2 Timelines From two separate sources, one is a 2nd degree source and the other is a 3rd degree source, MSFT is requesting changes to H1's networking topology. By extension, this topology will be need to be cabled for H2-4. The re-cabling on H2 was given a timeline of 45 days while H1 will be re-cabled while running workloads aka billing and that process was given a timeline of 4 months. H3 will be delivered with H4 as a supercluster, H4 hasn't begun cabling and will maintain December timeline. H1 recabling will take much longer than H2 because H1 is already accepted so the changes will be made during maintenance window in stages. H1 will be running live workloads and billing. I'm not sure when the 45 days started but H2 will be delivered either late Nov or Early Dec. Both H3 and H4 will be delivered as a super cluster Dec. What's the Issue This request comes after acceptance test while running workloads on H1 but before the supercluster networking before H1 and H2. The issue was described as networking bandwidth between racks within a scaleable unit. All of H1 counts 1 scalable unit. Networking physical distances are not as sensitive as Cray supercomputer days and spec is around 50 meters. This is important because it means that racks will not need to be moved, aka no changes to liquid cooling pipes or power distribution components. Cabling does take a long time because there are literally hundreds of thousands of cables that need to carefully cabled as wrong cable will take more time debugging than getting it right in the first place. The cabling team used for H1-4 too. However, internally the deadline is still 2026. Who is at Fault MSFT is a very large company with multiple team. Their bare metal team signed off because IREN met Nvidia DSX specs. However MSFT platform team when deploying software need a specific topology for their workload and was not communicated to the bare metal team. This explanation is based on the fact that this was not a test case in acceptance testing and found more than 1 month after acceptance and usage began. During this one month, it's likely that platform team deployed and only now did MSFT's AI research team started running workloads. Between IREN, Dell, MSFT - it's most likely MSFT's platform team did not gather requirements from MSFT's research team and did not relay the full requirements to MSFT's bare metal team. Dell is paid for cabling based on MSFT specs. And no, there cannot be one huge stress test to have maximized traffic between every rack within the SU because the networking bandwidth is maximized for workload traffic patterns. Every rack pair cannot simultaneously get each rack’s full bandwidth. Different topology maximizes for different workloads. IREN's supercluster topology is most likely rail-optimized, non blocking fat-tree.
2
2
152
47,279
$IREN Prince George UPDATE: We have what looks like a temporary storage facility onsite with a portable heater running (thermal pic) and 6 large black tanks all connected by one pipe, nearby. Any takers on what you think is going on here? I have my own theories.....
13
5
132
18,297
$IREN Prince George UPDATE: Redundancy! Two is One and One is None in the data center business. Notice there are two transformers and a firewall in between them for protection at IREN's company-owned substation. This substation brings CLEAN power in from BC Hydro's renewable energy grid. If the grid goes down generators and UPS's currently being installed take over the site's electrical load instantly with zero downtime.
11
18
253
15,974
$IREN Exactly
Know what you own. Flushes like this are not by choice. Decade long data centers are not weekly investments. Stay strong frens. $IREN
69
3,779
$IREN Prince George UPDATE: Hall #3 Closeup of two 95% complete segments (IMO). Notice the use of elevated cable trays for cable management. This is something we are seeing at all of IREN's miner-to-compute retrofits in Childress and BC sites. Cable trays dissipate heat much better than conduit, allow for quicker installation and easy access for site updates. This stays inline with IREN's modular/updatable site designs.
4
10
191
9,487
$IREN Prince George UPDATE: Thermal From Top Down View An update to follow yesterday's thermal video post. While all 4 data halls are drawing significant electricity, as shown by the heat signatures, it's important to note, that only two segments of hall #4 are showing significant heat. This adds up with company guidance from IREN's August, 2025 investor materials. If you look at the thermal image clip and company slide below. More details on this to come!
3
7
96
5,133
$IREN Prince George UPDATE: 10/9 Footage Halls are numbered 1-4 starting from the top down. Lots of progress has been made and redundancy added. More detailed posts to come breaking down different parts of the site. Stay tuned! The site is a little chopped up due to the limited amount of space, however each segment and hall are quite similar to the Mackenzie site.
9
12
231
35,559
Data Hall #1 is 4 Identical segments (all running based on thermal) -1 of 1 Hall switchgear in place -4 of 4 MERS in place -4 of 4 ATS in place -4 of 4 Medium-voltage stepdown transformers in place (34.5kv to 480v) -4 of 4 Low-voltage stepdown transformers in place -4 of 4 Segment switchgears in place -0 of 4 Generators in place 25% of cable trays installed and wiring terminations complete Data Hall #2 is 8 Identical segments (all running based on thermal) -1 of 1 Hall switchgear in place -8 of 8 MERS in place -8 of 8 ATS in place -8 of 8 Medium-voltage stepdown transformers in place (34.5kv to 480v) -8 of 8 Low-voltage stepdown transformers in place -8 of 8 Segment switchgears in place -2 of 8 Generators in place 50% of cable trays installed and wiring terminations complete Data Hall #3 is 8 Identical segments (all running based on thermal) -1 of 1 Hall switchgear in place -8 of 8 MERS in place -8 of 8 ATS in place -8 of 8 Medium-voltage stepdown transformers in place (34.5kv to 480v) -8 of 8 Low-voltage stepdown transformers in place -8 of 8 Segment switchgears in place -8 of 8 Generators in place 90%-100% of cable trays installed and wiring terminations complete Data Hall #4 is 8 Identical segments (2 of 8 segments running based on thermal) -1 of 1 Hall switchgear in place -4 of 8 MERS in place -4 of 8 ATS in place -8 of 8 Medium-voltage stepdown transformers in place (34.5kv to 480v) -4 of 8 Low-voltage stepdown transformers in place -4 of 8 Segment switchgears in place -4 of 8 Generators in place 50% of cable trays installed and wiring terminations complete
1
4
46
2,342