BREAKING: In an email released to a nearby community, the development team behind The Gathering at South Forsyth revealed they have secured financing for an NHL team and submitted a final packet for approval.
Developers also revealed that the first phase of construction is underway as of September 1st, 2026. A local contractor will grade and level the site through January 31st, 2027. Construction on the arena and adjacent buildings will start once leveling of the site is complete and will take an estimated 27 months. The entire site will be phased out over 7-10 years.
Based on an estimated completion of May 1st, 2029, a team could potentially be ready to play in the 2029/30 season. One important thing of note here is that according to an MOU with Forsyth County, an arena could not be built in phase one without NHL approval. While it has not been confirmed by the league that a team is being awarded, this is the most concrete information we’ve seen thus far.