🦔Oracle sent a force majeure notice on Project Jupiter, its AI data center in New Mexico built for the $400 billion Stargate deal with OpenAI. The campus needs a 17-mile gas pipeline to power its Bloom Energy fuel cells. New Mexico denied the pipeline permits twice. Oracle wants the right to delay payments if the site misses its 2028 opening. $18 billion in project loans are at 89 to 91 cents on the dollar. ORCL fell 5%.
My Take
Force majeure is for earthquakes and wars. Oracle filed one over a gas permit they got denied twice. A company with $167 billion in debt and a junk-adjacent credit rating just told its development partner it might not pay on time. I think Oracle's balance sheet is worse than the market has priced in, and this notice is the first public admission.
Twenty banks lent $18 billion for this project and they can't move the debt. Santander and Jefferies are stuck with more than they planned to hold. That loan assumed Oracle's backlog converts to revenue on schedule, but half the backlog is OpenAI, a company that burns cash faster than it earns it. SemiAnalysis has first power at this site in 2029. The banks underwrote 2028. I think the AI infrastructure bet cracks here first, in the loan market, before it ever shows up in stock prices, and the banks who funded the construction are the ones left with the bill.
Hedgie🤗
152
674
2,884
247,670