5/12 — SNOWY HYDRO SAYS IT CAN SEE EVERY COST. SO WHY IS THE PUBLIC LAST TO KNOW?
Snowy Hydro and its contractor agree on one thing. The owner could see the costs.
The contractor tells Parliament the 2023 reset gave Snowy Hydro "full visibility of project performance, costs and risks". Snowy Hydro's own submission says it has "full access to the contractor's costs".
Under the equity agreement behind the Commonwealth's $2.6 billion, it is meant to report "the projected cost to Project Completion" to government every month, according to the wording published by former senator Rex Patrick.
Snowy Hydro also reimburses the contractor's labour costs. The Auditor-General found it set no guardrails on what the new pay agreement would cost. So it was paying a bill it hadn't capped, with the figures in front of it.
In August the Energy Minister said he hadn't received the reassessment. The monthly report is a different document, but it is supposed to carry a projected cost to completion. So here is what Parliament should ask. What did those monthly reports say, and when?
Snowy Hydro's own action plan answers part of it.
One item reads "Document the monthly cost outcome reporting process and escalation pathways", and the plan lists it as still in progress. The monthly figure government gets comes from a process Snowy Hydro says isn't documented yet.
Snowy Hydro says releasing a number early could weaken its hand with the contractor. That's a fair concern. It doesn't explain why the owner with full visibility is the last to say what it sees.
But there's more…
Cold Hard Facts. Corrected when wrong. No misinformation.
What's your thoughts…?
Peter Lyndon-James 🇦🇺
Sources:
FGJV Submission 3 (para 70) and Snowy Hydro Submission 4 (pp.13, Appendix 1, Rec 4) to the JCPAA; Auditor-General Report No.39 (paras 2.84-2.86); Rex Patrick, Michael West Media, 8 May 2026.